Section 20:44:18:01 - Wiring permit required

The following electrical installations and electrical service entrances require a wiring permit:

(1) All electrical service entrances. A single wiring permit may be used for a temporary electrical service and a new service on a single project when both are installed by the same contractor, which must be stated on the wiring permit at the start of the project. Separate wiring permits are required if more than one contractor is involved; and
(2) Electrical wiring being performed under an owner's exemption.

All other electrical installations with a calculated inspection fee of $10 or greater require a wiring permit and minimum electrical inspection fee, as required by § 20:44:20:02.01, a specific fee as provided by chapter 20:44:20, or exclusions not requiring a wiring permit and noted under the provisions of article 20:44 and SDCL chapter 36-16.

S.D. Admin. R. 20:44:18:01

SL 1975, ch 16, § 1; 12 SDR 151, 12 SDR 155, effective 7/1/1986; 13 SDR 75, 13 SDR 95, effective 1/1/1987; 20 SDR 92, January 1, 1994; 20 SDR 222, effective 7/6/1994; transferred from § 20:44:04:01, August 12, 1994; 32 SDR 37, effective 9/1/2005; 37 SDR 236, effective 6/29/2011.

General Authority: SDCL 36-16-12.