S.D. Admin. R. 20:10:39:60

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:39:60 - Remediation

If the utility is required to conduct remediation, it shall commence such remediation in accordance with SDCL 49-47-3. Remediation efforts may include addressing other off-dairy sources. If a utility's contribution to stray voltage exceeds 50 percent of the preventive action level and the utility determines that another customer is a significant contributing source of stray voltage, the utility shall notify both the dairy and the other customer in writing.

S.D. Admin. R. 20:10:39:60

42 SDR 174, effective 6/21/2016

General Authority: SDCL 49-47-2.

Law Implemented: SDCL 49-47-2, 49-47-3.