S.D. Admin. R. 20:10:39:50

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:39:50 - Conducting the load box test

Except for dairies with three-phase balanced primary service, each of the following five steps for the load box test is conducted for at least two minutes:

(1) Step One: The load box is de-energized, the dairy remains "on," and the data is recorded;
(2) Step Two: The load box is de-energized, the dairy shut "off," and the data is recorded;
(3) Step Three: The load box is set to half load, the dairy shut "off," and the data is recorded;
(4) Step Four: The load box is set to full load, the dairy shut "off," and the data is recorded; and
(5) Step Five: The load box is set to full load, the dairy is turned "on," and the data is recorded.

For dairies with three-phase balanced primary service, the service provider performs steps one and two.

S.D. Admin. R. 20:10:39:50

42 SDR 174, effective 6/21/2016

General Authority: SDCL 49-47-2.

Law Implemented: SDCL 49-47-2, 49-47-3.