S.D. Admin. R. 20:10:39:38

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:39:38 - Reduced recording period for the 48 hour test

If a qualified analyst concludes that remediation by the utility is required because the preventive action level is exceeded and the portion of the stray current or voltage attributable to an off-farm source exceeds 50 percent of the preventive action level, the recording period may be reduced to no fewer than 24 hours.

S.D. Admin. R. 20:10:39:38

42 SDR 174, effective 6/21/2016

General Authority: SDCL 49-47-2.

Law Implemented: SDCL 49-47-2, 49-47-3.