S.D. Admin. R. 20:10:36:65

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:36:65 - Monitoring

A small generator facility of less than 25 kilowatts is not required to provide for remote monitoring of its electric output. A small generator facility of 25 kilowatts or more may be required by the public utility to provide data monitoring points and remote monitoring of the facility's electric output. If the facility is 25 kilowatts to 250 kilowatts and remote monitoring is required by the public utility, the public utility may require the interconnection customer to pay the data monitoring points costs and the remote monitoring costs shall be paid by the public utility. If the facility is over 250 kilowatts and remote monitoring is required by the public utility, the public utility may require the interconnection customer to pay the costs of the data monitoring points and remote monitoring.

S.D. Admin. R. 20:10:36:65

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.