S.D. Admin. R. 20:10:36:42

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:36:42 - Tier 3 interconnection

The public utility shall use the tier 3 interconnection review procedures for an application that does not qualify for tier 1 or tier 2 review and meets the following requirements:

(1) The small generator facility has an electric nameplate capacity rating of 2 megawatts or less;
(2) The proposed point of interconnection is not to a transmission line; and
(3) The small generator facility does not export power beyond the point of interconnection and utilizes low forward power relays or other protection functions that prevent power flow onto the EDS.

S.D. Admin. R. 20:10:36:42

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.