S.D. Admin. R. 20:10:36:34

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:36:34 - Tier 1 application completion

The tier 1 interconnection process is complete when:

(1) The application has passed the tier 1 screening criteria;
(2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection;
(3) The witness test, if conducted by the public utility, is successful;
(4) The parties execute a certificate of completion; and
(5) An interconnection agreement has been executed.

S.D. Admin. R. 20:10:36:34

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.