S.D. Admin. R. 20:10:36:31

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:36:31 - Tier 1 interconnection requirements

The public utility shall use the tier 1 review procedures for a small generator facility application that meets the following requirements:

(1) The proposed facility is inverter-based;
(2) The proposed facility has an electric nameplate capacity of 10 kilowatts or less;
(3) The proposed facility will use lab tested equipment only; and
(4) The proposed point of interconnection is not to a transmission line.

A public utility may not impose additional requirements to a tier 1 interconnection application.

S.D. Admin. R. 20:10:36:31

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.