S.D. Admin. R. 20:10:36:20

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:36:20 - Interconnection equipment cost responsibility

The public utility shall require the interconnection customer to be responsible for all expenses, including overheads, associated with owning, operating, maintaining, repairing, and replacing its interconnection equipment.

S.D. Admin. R. 20:10:36:20

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.