Section 20:10:22:10 - Demand for facility

The applicant shall provide a description of present and estimated consumer demand and estimated future energy needs of those customers to be directly served by the proposed facility. The applicant shall also provide data, data sources, assumptions, forecast methods or models, or other reasoning upon which the description is based. This statement shall also include information on the relative contribution to any power or energy distribution network or pool that the proposed facility is projected to supply and a statement on the consequences of delay or termination of the construction of the facility.

S.D. Admin. R. 20:10:22:10

5 SDR 1, effective 7/25/1978; 12 SDR 151, 12 SDR 155, effective 7/1/1986.

General Authority: SDCL 49-41B-35.