S.D. Admin. R. 20:10:21:07

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:21:07 - Proposed transmission facilities

For proposed transmission facilities for the ensuing 10 calendar years, the utility shall provide information as follows:

(1) General anticipated location and reasons for the selection;
(2) Probable type and proposed transmission voltage;
(3) Description of anticipated associated facilities;
(4) Projected date of removal from service; and
(5) Total estimated capital cost.

S.D. Admin. R. 20:10:21:07

4 SDR 7, effective 11/13/1977; 12 SDR 151, 12 SDR 155, effective 7/1/1986.

General Authority: SDCL 49-41B-35.

Law Implemented: SDCL 49-41B-3(1), 49-41B-3(4).