S.D. Admin. R. 20:09:26:15

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:09:26:15 - Modification of authority financing terms

The authority may amend the amount of the housing infrastructure program funding at any time before closing, based on the final itemization of the total project cost. The executive director of the authority may approve and authorize an increase in the housing infrastructure program funding in an amount not to exceed five percent of the initial amount if the executive director finds the increase is justified by an increase in costs applicable to the public infrastructure and is necessary or desirable for the successful construction and operation of the public infrastructure.

S.D. Admin. R. 20:09:26:15

49 SDR 125, effective 7/3/2023

General Authority: SDCL 11-15-6.

Law Implemented: SDCL 11-15-1 to 11-5-5, inclusive.