S.C. Code Regs. § § 63-716

Current through Register Vol. 48, No. 11, November 22, 2024
Section 63-716 - Special Provisions Applicable to Non-bonded Projects
A. By submission of a bid on a non-bonded project, the DBE grants permission to the Department to issue joint checks to suppliers, vendors or subcontractors who supply materials, render services or perform work on the contract when joint checks are, in the Department's judgment, necessary or desirable.
B. A bid on a non-bonded project shall include a list of all suppliers, vendors or subcontractors who the DBE proposes to use in performing the contract.
C. A DBE on a non-bonded project shall not permit a subcontractor to perform work on a contract until the subcontractor and the subcontract have been approved by the Department. To obtain such approval after the award of the contract, the Contractor must submit a request for approval and a copy of the executed subcontract to the Department's Official Engineer. The Department will approve or disapprove such subcontractor within a reasonable amount of time after the receipt of such request.
D. A DBE on a non-bonded project shall not incorporate materials or supplies into the work of a contract until the executed invoice or purchase agreement has been submitted to the Department. The DBE must submit the copy of the invoice or purchase agreement to the Official Engineer, as appropriate.
E. Failure to obtain approval for subcontractors or subcontracts, or failure to submit copies of subcontracts, purchase agreements or invoices, shall constitute, at the Department's option, a default of the contract.
F. Termination of any non-bonded contract for default of the contractor renders the contractor ineligible for any further Department non-bonded contracts for a minimum period of two years from the date of the Notice of Default. The Department may also consider defaulting contractors ineligible to bid on other Department contracts pursuant to the provisions of Section 102.03(e) of the Department's Standard Specifications for Highway Construction and ineligible for approval as a DBE subcontractor on any Department contract with a DBE goal.
G. In the event of default, the provisions of Section 108.10 of the Department's Standard Specifications for Highway Construction shall apply, with the Department acting as surety. Any costs or charges incurred by the Department, or for which the Department, acting as such surety, shall become liable as a result of the default, shall be charged against the defaulting DBE contractor. The costs and charges may include, but are not limited to: (1) charges incident to preparing bid proposal and arranging for work to be resumed; and, (2) the excess of the expense of completing the work under the contract deducted from any monies due or which may be due the DBE contractor. The defaulting DBE contractor shall reimburse or indemnify the Department, as surety, for all such costs or charges. The defaulting DBE contractor shall be ineligible to bid as a prime contractor on any Department contracts and shall be ineligible for approval as a DBE subcontractor on any Department contract with a DBE goal until the DBE contractor has reimbursed the Department or made acceptable arrangements to reimburse the Department for such costs or charges.

S.C. Code Regs. § 63-716

Added by State Register Volume 16, Issue No. 6, eff June 26, 1992. Amended by State Register Volume 24, Issue No. 4, eff April 28, 2000.