The Department may require bidders to have a minimum contractor performance score to bid on a project. The Department shall determine the appropriate minimum score for a project based on an evaluation of criteria that includes, but is not limited to: design complexity, critical time constraints, environmental sensitivity, complex traffic control, location in densely populated areas, need for specialized equipment, high traffic volume, and project cost. All prequalified contractors whose contractor performance score is below the minimum shall not be allowed to bid on projects that require a minimum required contractor performance score. Prequalified contractors who have never had or do not have a current contractor performance score will not be subject to this bidding restriction.
S.C. Code Regs. § 63-307