Section 61-82.III - Proper closeout of package plantsPackage plants shall be drained in accordance with one of the following procedures:
a. Sewage may be pumped into the treatment facility or receiving system replacing the package plant, provided that the rate is such that overloading of the replacement system is prevented and provided that permission is obtained from the owner of the replacement system; orb. Sewage may be pumped into portable tanks for transfer and disposal in a sewer system, provided that permission is obtained from the owner of the receiving system.S.C. Code Regs. § 61-82.III