Section 61-79.265.W.444 - Inspections
(a) During construction or installation, liners and cover systems (e.g., membranes, sheets, or coatings) must be inspected for uniformity, damage and imperfections (e.g., holes, cracks, thin spots, or foreign materials). Immediately after construction or installation, liners must be inspected and certified as meeting the requirements of 265.443 by a qualified Professional Engineer. This certification must be maintained at the facility as part of the facility operating record. After installation, liners and covers must be inspected to ensure tight seams and joints and the absence of tears, punctures, or blisters.
(b) While a drip pad is in operation, it must be inspected weekly and after storms to detect evidence of any of the following:
(1) Deterioration, malfunctions or improper operation of runon and runoff control systems;
(2) The presence of leakage in and proper functioning of leakage detection system.
(3) Deterioration or cracking of the drip pad surface.

S.C. Code Regs. 61-79.265.W.444

Added by State Register Volume 16, Issue No. 12, eff December 25, 1992. Amended by State Register Volume 32, Issue No. 6, eff June 27, 2008.

See 265.443(m) for remedial action required if deterioration or leakage is detected.