Section 61-79.265.B.19 - Construction quality assurance program
(a) CQA program.
(1) A construction quality assurance (CQA) program is required for all surface impoundment, waste pile, and landfill units that are required to comply with 265.221(a), 265.254, and 265.301(a). The program must ensure that the constructed unit meets or exceeds all design criteria and specifications in the permit. The program must be developed and implemented under the direction of a CQA officer who is a registered professional engineer.
(2) The CQA program must address the following physical components, where applicable:
(i) Foundations;
(ii) Dikes;
(iii) Low-permeability soil liners;
(iv) Geomembranes (flexible membrane liners);
(v) Leachate collection and removal systems and leak detection systems; and
(vi) Final cover systems.
(b) Written CQA plan. Before construction begins on a unit subject to the CQA program under paragraph (a) of this section, the owner or operator must develop a written CQA plan. The plan must identify steps that will be used to monitor and document the quality of materials and the condition and manner of their installation. The CQA plan must include:
(1) Identification of applicable units, and a description of how they will be constructed.
(2) Identification of key personnel in the development and implementation of the CQA plan, and CQA officer qualifications.
(3) A description of inspection and sampling activities for all unit components identified in paragraph (a)(2) of this section, including observations and tests that will be used before, during, and after construction to ensure that the construction materials and the installed unit components meet the design specifications. The description must cover: Sampling size and locations; frequency of testing; data evaluation procedures; acceptance and rejection criteria for construction materials; plans for implementing corrective measures; and data or other information to be recorded and retained in the operating record under 265.73.
(c) Contents of program.
(1) The CQA program must include observations, inspections, tests, and measurements sufficient to ensure:
(i) Structural stability and integrity of all components of the unit identified in paragraph (a)(2) of this section;
(ii) Proper construction of all components of the liners, leachate collection and removal system, leak detection system, and final cover system, according to permit specifications and good engineering practices, and proper installation of all components (e.g., pipes) according to design specifications;
(iii) Conformity of all materials used with design and other material specifications under 264.221, 264.251, and 264.301 of this chapter.
(2) The CQA program shall include test fills for compacted soil liners, using the same compaction methods as in the full-scale unit, to ensure that the liners are constructed to meet the hydraulic conductivity requirements of 264.221(c)(1), 264.251(c)(1), and 264.301(c)(1) of this chapter in the field. Compliance with the hydraulic conductivity requirements must be verified by using in-situ testing on the constructed test fill. The test fill requirement is waived where data are sufficient to show that a constructed soil liner meets the hydraulic conductivity requirements of 264.221(c)(1), 264.251(c)(1), and 264.301(c)(1) of this chapter in the field.
(d) Certification. The owner or operator of units subject to 265.19 must submit to the Department by certified mail or hand delivery, at least 30 days prior to receiving waste, a certification signed by the CQA officer that the CQA plan has been successfully carried out and that the unit meets the requirements of 265.221(a), 265.254, or 265.301(a). The owner or operator may receive waste in the unit after 30 days from the Department receipt of the CQA certification unless the Department determines in writing that the construction is not acceptable, or extends the review period for a maximum of 30 more days, or seeks additional information from the owner or operator during this period. Documentation supporting the CQA officers certification must be furnished to the Department upon request.

S.C. Code Regs. 61-79.265.B.19