S.C. Code Regs. § § 61-62.68.H.215

Current through Register Vol. 48, No. 9, September 27, 2024
Section 61-62.68.H.215 - Permit content and Department requirements
(a) These requirements apply to any stationary source subject to Regulation 61-62.68 and Regulation 61-62.70. The Regulation 61-62.70 permit for the stationary source shall contain:
(1) A statement listing Regulation 61-62.68 as an applicable requirement;
(2) Conditions that require the source owner or operator to submit:
(i) A compliance schedule for meeting the requirements of Regulation 61-62.68 by the date provided in Sections 68.10(a) through (f) and 68.96(a) and (b)(2)(i), or;
(ii) As part of the compliance certification submitted under Section 61-62.70.6(c)(5), a certification statement that the source is in compliance with all requirements of Regulation 61-62.68, including the registration and submission of the RMP.
(b) The owner or operator shall submit any additional relevant information requested by the Department.
(c) For Regulation 61-62.70 permits issued prior to the deadline for registering and submitting the RMP and which do not contain permit conditions described in paragraph (a) of this section, the owner or operator or the Department shall initiate permit revision or reopening according to the procedures of Section 61-62.70.7 to incorporate the terms and conditions consistent with paragraph (a) of this section.
(d) The Department may delegate the authority to implement and enforce the requirements of paragraph (e) of this section to a state or local agency or agencies other than the Department. An up-to-date copy of any delegation instrument shall be maintained by the Department. The state may enter a written agreement with the Administrator under which EPA will implement and enforce the requirements of paragraph (e) of this section.
(e) The Department will, at a minimum:
(1) Verify that the source owner or operator has registered and submitted an RMP or a revised plan when required by Regulation 61-62.68;
(2) Verify that the source owner or operator has submitted a source certification or in its absence has submitted a compliance schedule consistent with paragraph (a)(2) of this section;
(3) For some or all of the sources subject to this section, use one or more mechanisms such as, but not limited to, a completeness check, source audits, record reviews, or facility inspections to ensure that permitted sources are in compliance with the requirements of Regulation 61-62.68; and
(4) Initiate enforcement action based on paragraphs (e)(1) and (e)(2) of this section as appropriate.

S.C. Code Regs. § 61-62.68.H.215