S.C. Code Regs. § § 61-58.1.K

Current through Register Vol. 48, No. 10, October 25, 2024
Section 61-58.1.K - Requirements for Obtaining Approval to Place Permitted Construction into Operation
(1) Newly-constructed facilities shall not be placed into operation until written approval is issued by the Department, except where it is allowed by a general construction permit. Upon completion of permitted construction, the professional engineer shall make arrangements with the Department for final inspection. Prior to this inspection, the professional engineer shall submit to the Department a letter certifying that construction is complete and in accordance with the approved plans and specifications. This letter must specifically identify the project by permit number. If the project was not completed in accordance with the approved plans and specifications, the professional engineer shall so state and shall outline any deviations to the permitted project. No written approval shall be issued to place a drinking water construction project into operation until written approval is obtained to place any associated wastewater construction into operation. The following information, where applicable, shall be submitted with the professional engineer's letter of certification:
(a) Results of chemical, physical, radiological, and bacteriological analyses of new sources and/or treated water. These analyses shall be performed by a certified laboratory.
(b) Results of bacteriological analyses following disinfection, including chlorine residuals at the time of collection, which have been conducted within thirty (30) days of the request for final approval. These analyses shall be performed by a certified laboratory.
(c) Results of pressure/leakage test conducted on water lines;
(d) Record drawings of construction if the construction deviated from that approved;
(e) Completed Water Well Record form;
(f) Geophysical/mechanical well logs;
(g) Results of pumping test as required by R.61-58.2(B)(12)(B)(12).
(h) Letter of acceptance from organization responsible for operation and maintenance (must be the same as shown on the application for permit to construct form);
(i) Paint coating(s) used for water storage tank(s);
(j) Copy of recorded legal easement(s) and/or deed restriction(s) for protection of well pollution free radius;
(k) Proof of registration with the S. C. Public Service Commission for new privately owned utilities and homeowner associations;
(l) Proof of testing of all backflow prevention assemblies installed; and,
(m) Copies of any information specified in a special condition of a Department construction permit.
(2) Failure to obtain written approval from the Department prior to placing any newly constructed drinking water facilities into operation is a violation of the Act (Code Section 44-55-40 ) and is subject to an enforcement action by the Department. Where a person has failed to obtain a permit to construct, an application for permit must be submitted to include record drawings carrying the seal and signature of a professional engineer.