(i) New/increased capacity NPDES or land application permits | 180 Days | |
(ii) Construction Permit for new treatment plant or expansion with increased volume, mass loading, or loading, or addition of pollutant to be controlled. | 120 Days (or 20 Days beyond effluent discharge permit issuance, whichever is greater) | |
(iii) Construction Permit for treatment plant upgrade (without expansion and no change in effluent discharge permit limits) | 90 Days | |
(iv) Construction permit for pre-treatment system | 90 Days | |
(v) Construction Permit for sewer systems (including pump stations and force main systems) | 60* Days *Add 45 days if separate navigable waterway permit is applicable | |
(vi) Storm water discharge under General Permit | 7 Days | |
(vii) Water Quality Certification | 180 Days | |
(b) | Agricultural Waste Management Plan Application | |
(i) Swine Facilities | ||
1. Facilities with a capacity of 420,000 pounds or more of production animal live weight at any one time | 120 Days | |
2. Facilities with a capacity of less than 420,000 pounds of normal production animal live weight at any one time | 90 Days | |
(ii) Other Animal Facilities | ||
1. Dry Manure/Litter Operation | 90 Days | |
2. Wet Manure/Litter Operation | 120 Days | |
(c) | Air Quality: | |
(i) Construction permit | 90 Days (Except for permits issued under the NESHAP Regulation [R.61-62.63] which provides 105 days for permit issuance.) | |
(ii) Operating permit | 90 Days | |
(iii) PSD Construction Permit | 270 Days | |
(iv) Title V Operating Permit | 540 Days | |
(d) | Laboratory Certification: | |
(e) | (i) Initial certification Radioactive Materials licenses: | 90 Days |
(i) New license - on-site disposal,broad license | 30 Days | |
(ii) New license - storage/treatment | 180 Days | |
(iii) License renewal - annual | 30 Days | |
(iv) Transporter permit | 10 Days | |
(f) | Hazardous and Mixed Waste Management: | |
(i) Commercial Hazardous Waste Facilities | 990 Days | |
(ii) Non-Commercial Hazardous Waste Facilities | 540 Days |
Applications for permit modifications which add or delete units or which change the capacity of permitted units will be processed within The time schedules above.
(g) | Solid Waste Management. |
(i) Municipal Solid Waste Landfill Permit: | |
1. Solid Waste Landfill Siting Study: | 60 Days |
a. Preliminary Hydrogeologic Characterization Report | |
b. Site Hydrogeologic Characterization Work Plan | 90 Days |
c. Site Hydrogeologic Characterization Report | 120 Days |
2. Permit Application | 360 Days |
(ii) Industrial Solid Waste Landfill Permit: | |
1. Solid Waste Landfill Siting Study: | |
a. Preliminary Hydrogeologic Characterization Report | 60 Days |
b. Site Hydrogeologic Characterization Workplan | 90 Days |
c. Site Hydrogeologic Characterization Report | 120 Days |
2. Permit Application | 360 Days |
(iii) Municipal Incinerator Ash Landfill Permit: | |
1. Solid Waste Landfill Siting Study: | |
a. Preliminary Hydrogeologic Characterization Report | 60 Days |
b. Site Hydrogeologic Characterization Workplan | 90 Days |
c. Site Hydrogeologic Characterization Report | 120 Days |
2. Permit Application | 360 Days |
(iv) Municipal Solid Waste Incineration Permit | 180 Days |
(v) Construction, Demolition and Land-Clearing Debris Landfill Permit | 120 Days |
(vi) Waste Tire Permit (Processing, Collection and Disposal Permit) | 90 Days |
(vii) Waste Tire Hauler Registration | 30 Days |
(viii) Transfer Station Permit | 90 Days |
(ix) Research, Development and Demonstration Permit | 90 Days |
(x) Municipal Solid Waste Processing Permit | 90 Days |
(xi) Lead-Acid Battery Facility Registration | 30 Days |
(xii) Yard Trash Composting Facility Registration | 30 Days |
(h) | Infectious Waste Management: |
(i) Treatment facility | 270 Days |
(ii) Intermediate handling facility | 270 Days |
(i) | Drinking Water Permits: |
(i) Drinking Water Construction | 45 Days |
(ii) Recreational Waters | 15 Days |
(iii) UST Construction Permit 15 Days In Coastal Zone | 45 Days |
(iv) UST Operating Permit | 10 Days |
(v) UIC Construction Permit | 60 Days |
(vi) UIC Operating Permit | 45 Days |
(i) Individual Residential Well | 48 Hours |
(ii) Irrigation Well | 48 Hours |
S.C. Code Regs. § 61-30.H