S.C. Code Regs. § § 61-15.A.6.602

Current through Register Vol. 48, 12, December 27, 2024
Section 61-15.A.6.602 - Extension Request
1. A Certificate of Need extension shall be requested in writing by the applicant at least thirty (30) calendar days before the expiration date of the Certificate of Need.
2. The written request for an extension shall include at least the following:
a. A detailed description of any changes in the configuration, costs, services, or scope of the project.
b. A detailed description and documentation of any progress on the project including preparation of construction drawings, the securing of necessary funds and building permits, and commencement of any construction.
c. An estimated timetable for commencement and completion of all remaining components of the project.
d. Documentation of compliance with the approved timetable or documented evidence that extenuating circumstance beyond the control of the applicant if the timetable was not met.

S.C. Code Regs. § 61-15.A.6.602

Amended by State Register Volume 36, Issue No. 5, eff May 25, 2012; State Register Volume 48, Issue No. 04, eff. 4/26/2024.