S.C. Code Regs. § § 61-107.19.V.C.258.26

Current through Register Vol. 48, No. 10, October 25, 2024
Section 61-107.19.V.C.258.26 - Run-on/run-off Control Systems
a. Owners/operators of all Class Three landfills shall design, construct, and maintain:
(1) A run-on control system to prevent flow onto the active portion of the landfill during the peak discharge from a 25-year storm; and,
(2) A run-off control system from the active portion of the landfill to collect and control at least the water volume resulting from a 24-hour, 25-year storm.
b. Run-off from the active portion of the landfill shall be handled in accordance with 258.27.a. below.

S.C. Code Regs. § 61-107.19.V.C.258.26