300-00-00 R.I. Code R. § 1.10

Current through August 19, 2024
Section 300-RICR-00-00-1.10 - Application review and evaluation criteria
A. Application review
1. In order for an application to be evaluated, scored and ranked it must be deemed complete by OER. In order to be deemed complete an application must contain all required information, forms, and supplemental documents as required by OER
2. Applications shall be reviewed for completeness within five (5) business days of receipt. OER shall notify the applicant if an application is incomplete and identify the missing documentation. The applicant shall submit the missing documentation within five (5) business days of notification in order to be considered for the funding round. If the applicant does not submit the required information in the designated time period the application will be denied and the applicant will need to re-submit a complete application in a subsequent application period.
B. Evaluation criteria
1. Evaluation criteria for applications
a. All complete applications will be evaluated based on criteria identified in the application, which may include, but are not limited to, the following:
b. Renewable energy project applications (Solar PV or Wind)
(1) Energy output of the installed system (kWh)
(2) Installed price per watt of the installation
(3) Green initiatives or lead by example
(4) Shovel ready - timeliness and readiness
c. Energy efficiency project applications
(1) Energy savings and comprehensiveness
(2) Green initiatives or lead by example
(3) Shovel ready - timeliness and readiness
d. Criteria for other technologies, as identified in Section 1.8 E. of this Part, shall be determined as necessary.
e. Additional criteria:
(1) Distressed community status.
(2) Energy efficiency and renewable energy projects in the same application period.

300 R.I. Code R. § 300-RICR-00-00-1.10