Section 250-RICR-40-25-1.8 - Application Evaluation
A. Evaluation Criteria: The Mosquito Abatement Board shall consider several criteria in rating applications, including but not limited to the following:
1. Relationship of the proposed project to the program objective of minimization of pesticide use and the minimal disruption of natural environments.
2. Probability that the proposed work will be completed successfully;
3. Capability of personnel;
4. Adequacy of facilities and equipment;
5. Availability of alternative funding to accomplish objectives;
6. Cost-effectiveness of the project;
7. Likelihood that the proposed project will make a long-term contribution to mosquito abatement in the community;
8. Evidence that all necessary safety precautions will be taken; and,
9. Evidence that all State and Federal permits, clearances, or statements of non-applicability have been applied for or granted.