Section 250-RICR-140-05-6.9 - Sampling of Processed Soil at Processor's Facility (Per Section 6.2(H) of this Part)
A. The following is a guideline that represents a minimum sampling and testing strategy. Additional sampling and testing may be desirable at a given facility, on a case-by-case, or where required by the party that will be accepting the soil for re-use. Details of the actual tests and analyses will be based on any requirements of the accepting party.
1. Each 100 cubic yards of processed soil shall be sampled and tested. From each 100 cubic yards of processed soil in the holding area take five grab samples, each from a depth of at least one foot in the pile. The locations of the sample points shall be from designated zones within each 100 cubic yards grid, i.e., north, south, east, west, and center. The grab sample will, in turn, be composited into one sample for test purposes and a portion of this sample will be tested in the laboratory. If the test results indicate that the soil is sufficiently void of contaminants, then it can be moved out of the holding area and stored in other areas of the process facility.

250 R.I. Code R. 250-RICR-140-05-6.9

Amended effective4/22/2020