Section 250-RICR-120-05-36.7 - Compliance Schedule
A. Unless otherwise specified compliance with the provisions of this Regulation shall be achieved by the following dates:
1. Solvent cleaning machines that commenced construction or reconstruction before November 29, 1993, shall achieve compliance with this Regulation by January 1, 1997.
2. Solvent cleaning machines that commenced construction or reconstruction on or after November 29, 1993, shall achieve compliance with this Regulation immediately upon startup or by April 8, 1996, whichever is later.
3. Any batch vapor cleaning machine with a solvent/air interface that uses trans 1,2-dichloroethene or n-propyl bromide shall achieve compliance with §§ 36.10(C), (F), and (G) of this Part immediately upon first use of that solvent or by April 9, 2009, whichever is later.
B. Facilities complying with the facility wide emissions limits for hazardous air pollutants in § 36.8(Q) of this Part, shall achieve compliance by the following dates:
1. Solvent cleaning machines that commenced construction or reconstruction on or before August 17, 2006, shall achieve compliance with the facility wide emissions standards for hazardous air pollutants in § 36.8(Q) of this Part, by May 3, 2010.
2. Solvent cleaning machines that commenced construction or reconstruction on or after August 17, 2006, shall achieve compliance with the facility wide emissions standards for hazardous air pollutants in § 36.8(Q) of this Part, by May 3, 2007 or immediately upon startup, whichever is later.

250 R.I. Code R. 250-RICR-120-05-36.7

Adopted effective 1/13/2019