52 Pa. Code § 69.2

Current through Register Vol. 54, No. 50, December 14, 2024
Section 69.2 - Fuel and power planning
(a) A utility should submit to the Commission its long-term generation plans and a statement of how the plans affect fuel purchasing policy and planning. A plan should be submitted each time there are revisions. A utility should adopt fuel purchasing strategies that provide lowest reasonable cost with maximum flexibility. It should strive to stimulate competition by purchasing from numerous suppliers.
(b) [Reserved].

52 Pa. Code § 69.2

The provisions of this § 69.2 amended October 18, 1985, effective 10/19/1985, 15 Pa.B. 3730.

The provisions of this § 69.2 issued under Public Utility Code, the Public Utility Code, 66 Pa.C.S. § § 501, 1301 and 1307.

This section cited in 52 Pa. Code § 69.1 (relating to general).