4 Pa. Code § 58.418

Current through Register Vol. 54, No. 38, September 21, 2024
Section 58.418 - Ten-day prompt pay policy

A prime contractor that has a contract for nonconstruction goods and services shall pay to SB subcontractors the invoiced amount due for work completed or services provided under the subcontract within 10 days after receipt of payment from the Commonwealth.

4 Pa. Code § 58.418

Adopted by Pennsylvania Bulletin, Vol 54, No. 11. March 16, 2024, effective 3/16/2024