28 Pa. Code § 1171a.25

Current through Register Vol. 54, No. 45, November 9, 2024
Section 1171a.25 - Renewal of an approval issued to a laboratory

An approved laboratory wishing to renew its approval under this chapter shall, not more than 6 months nor less than 4 months prior to the expiration of the approval, submit an application under § 1171a.23 (relating to approval of laboratories) and update the information required to be submitted with the application as necessary.

28 Pa. Code § 1171a.25

Adopted by Pennsylvania Bulletin, Vol 53, No. 09. March 4, 2023, effective 3/4/2023

This section cited in 28 Pa. Code § 1171a.22 (relating to laboratories generally).