25 Pa. Code § 277.101

Current through Register Vol. 54, No. 37, September 14, 2024
Section 277.101 - Two-phase process

A person or municipality may submit an application for a permit to operate a construction/demolition waste landfill in two phases, known as Phase I and Phase II, under this subchapter. Approval by the Department of a Phase I application does not constitute or guarantee approval for the Phase II permit application, issuance of the permit or authority to operate a construction/demolition waste landfill.

25 Pa. Code § 277.101