25 Pa. Code § 109.501

Current through Register Vol. 54, No. 25, June 22, 2024
Section 109.501 - General permit requirements
(a) A person may not construct a public water system without first having obtained a construction permit from the Department under § 109.503 (relating to public water system construction permits) except as provided in §§ 109.502 and 109.505 (relating to permitting of currently operating systems; compliance deadlines; and requirements for noncommunity water systems).
(b) A person may not substantially modify a permitted public water system without first obtaining an amended construction permit from the Department under § 109.503(b).
(c) A person may not operate a public water system without first having obtained an operation permit from the Department under § 109.504 (relating to public water system operation permits) except as provided in §§ 109.502 and 109.505.
(d) A person may not operate a substantially modified facility without first obtaining an amended operation permit from the Department under § 109.504.

25 Pa. Code § 109.501

The provisions of this § 109.501 adopted December 7, 1984, effective 12/8/1984, 14 Pa.B. 4479; amended May 15, 1992, effective 5/16/1992, 22 Pa.B. 2621.