If the Department finds that construction of a dam or reservoir has substantially disrupted aquatic life to preclude natural restoration of the stream ecology within a reasonable period of time, the permittee shall be required to submit and implement a plan to restore the aquatic life of the stream to its prior condition, to the maximum extent possible. The plan shall be subject to review and modification by the Department in consultation with the Fish and Boat Commission and must include, but not be limited to, the following:
25 Pa. Code § 105.123
The provisions of this § 105.123 amended under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).