25 Pa. Code § 87.121

Current through Register Vol. 54, No. 25, June 22, 2024
Section 87.121 - Hydrologic balance: permanent postmining renovation of sedimentation ponds, diversions, impoundments and treatment facilities

At the completion of surface mining activities, the person who conducts the surface mining activities shall renovate all permanent sedimentation ponds, diversions, impoundments and treatment facilities to meet criteria specified in the detailed design plan for the permanent structures and impoundments, unless the permittee demonstrates that the facility or structure meets the requirements of this subchapter.

25 Pa. Code § 87.121

The provisions of this § 87.121 adopted December 19, 1980, 10 Pa.B. 4789, effective 7/31/1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective 7/31/1982, 12 Pa.B. 2382.