25 Pa. Code § 78a.33

Current through Register Vol. 54, No. 45, November 9, 2024
Section 78a.33 - Effect of panel on time for permit issuance

The period of time during which the objections are being considered by a full panel will not be included in the 45-day period for the issuance or denial of a permit under section 3211(e) of the act (relating to well permits).

25 Pa. Code § 78a.33

This section cited in 25 Pa. Code § 78a.25 (relating to conferences-general).