Current through Register Vol. 54, No. 45, November 9, 2024
Section 77.131 - Progress reportWithin 90 days after commencement of surface mining operations and each year thereafter, unless modified or waived by the Department for cause, the operator shall file in triplicate an operations and progress report with the Department, on a form prescribed and furnished by Department. The following information shall be included:
(1) The name and permit number of the operation.(2) The location of the operation as to county and township and with reference to the nearest public highway.(3) A description of the tracts.(4) The name and address of the landowner or an authorized representative.(5) An annual report of the type and quantity of mineral produced, number of employes and days worked.(6) A report of fatal and nonfatal accidents for the previous year.(7) The current status of the reclamation work performed in the pursuit of the approved reclamation plan.(8) Other or further information the Department may reasonably require.The provisions of this §77.131 adopted March 16, 1990, effective 3/17/1990, 20 Pa.B. 1643.