Current through Register Vol. 54, No. 44, November 2, 2024
Section 76.61 - Construction progress reports(a) Written construction progress reports shall be submitted to the Department quarterly for development and demonstration projects by the development agency, in consultation with the designer of the plans and specifications and the construction contractor. A more frequent progress report may be required for some projects, if set forth in the agreement.(b) Progress reports shall fully describe in chart or narrative format the progress achieved in relation to the approved schedule and project milestones. Special delays or problems shall be fully explained. Progress reports shall be attested to by the project engineer.The provisions of this §76.61 adopted January 30, 1976, effective 2/16/1976, 6 Pa.B. 157.