Section 71.59 - Delegated agency administration of new land development planning requirements
(a) When the Department has delegated the authority to review and approve subdivisions for new land developments to a delegated agency, the regulatory provisions of the Department in §§ 71.54 and 71.55 (relating to Department administration of new land development planning requirements for revisions; and exceptions to the requirement to revise the official plan for new land development) shall be administered by the delegated agency except that the time limits for review shall be in accordance with subsection (c).
(b) A new land development proposal submitted as a revision or an exception to the requirement to revise may be approved by the delegated agency as a supplement to the official plan of the municipality.
(c) The delegated agency shall determine if a submission is complete within 10 working days of its receipt. Delegated agencies shall approve or disapprove supplements within 60 days of the date of a complete submission or additional time that the applicant and delegated agency may agree to in writing.
(d) If planning modules for new land development propose service by sewerage facilities requiring a new or modified permit from the Department under The Clean Streams Law, the new land development planning module shall be forwarded to the Department for final action.

25 Pa. Code § 71.59

The provisions of this §71.59 adopted November 7, 1997, effective 11/8/1997, 27 Pa.B. 5877.