Section 918-050-0170 - Statewide Fee Methodology for Deferred Submittals

A fee charged for processing and reviewing deferred plan submittals shall be an amount equal to a percentage, determined by the municipality, of the building permit fee calculated according to OAR 918-050-0110(2) and (3) using the value of the particular deferred portion or portions of the project, with a set minimum fee. This fee is in addition to the project plan review fee based on the total project value.

Or. Admin. Code § 918-050-0170

BCD 12-2002, f. 6-28-02, cert. ef. 7-1-02; BCD 31-2005, f. 12-30-05, cert. ef. 1-1-06; BCD 27-2008, f. ef.12-12-08, cert. ef. 1-1-09

Stat. Auth.: ORS 455.048 & 455.055

Stats. Implemented: ORS 455.046 & 455.055