Or. Admin. Code § 860-091-0030

Current through Register Vol. 64, No. 1, January 1, 2025
Section 860-091-0030 - Eligible Renewable Energy Projects
(1) Projects used to comply with the standard in ORS 469A.210(2) must be an Oregon Renewable Portfolio Standard-approved generator; and
(2) The eligible portion of a project's capacity used to comply with the standard in ORS 469A.210(2) is the percentage of annual project costs paid for by Oregon retail customers.

Or. Admin. Code § 860-091-0030

PUC 12-2021, adopt filed 12/21/2021, effective 12/21/2021

Statutory/Other Authority: ORS 756.060, ORS 469A.200 & ORS 469A.210

Statutes/Other Implemented: ORS 469A.210