Section 860-084-0020 - Solar Photovoltaic Capacity Standard

By January 1, 2020, each electric company must own or contract to purchase the capacity and output of qualifying solar photovoltaic systems to meet and maintain the following minimum solar photovoltaic capacity standards:

(1) Portland General Electric: 10.9 megawatts
(2) Pacific Power: 8.7 megawatts
(3) Idaho Power Company: 0.5 megawatts.