Or. Admin. Code § 860-082-0010

Current through Register Vol. 63, No. 12, December 1, 2024
Section 860-082-0010 - Waiver
(1) Upon request or its own motion, the Commission may waive any of the Division 082 rules for good cause shown. A request for waiver must be made in writing, unless otherwise allowed by the Commission.
(2) A public utility and an applicant or interconnection customer may agree to reasonable extensions to the required timelines in these rules without requesting a waiver from the Commission.
(a) If a public utility and an applicant or interconnection customer are unable to agree to waive a timeline, then the public utility, applicant, or interconnection customer may request that the Commission grant a waiver.
(b) In deciding whether to grant a waiver of a timeline, the Commission will consider the number of pending applications for interconnection review and the type of applications, including review level, facility type, and facility size.
(c) Waiver of a timeline, whether by agreement or Commission order, does not affect an application's queue position.

Or. Admin. Code § 860-082-0010

PUC 10-2009, f. & cert. ef. 8-26-09; PUC 6-2011, f. & cert. ef. 9-14-11

Stat. Auth.: ORS 183, 756 & 757

Stats. Implemented: ORS 756.040, 756.060