Or. Admin. Code § 860-028-0220

Current through Register Vol. 63, No. 11, November 1, 2024
Section 860-028-0220 - Resolution of Factual Disputes
(1) If a pole occupant and pole owner have a dispute over facts that the pole occupant and pole owner must resolve so that the pole owner can impose appropriate sanctions, or in the event that a pole occupant is alleging that a pole owner is unreasonably delaying the approval of a written contract or the issuance of a permit, then either the pole owner or the pole occupant may request a settlement conference before the Joint-Use Association (JUA). The party making the request shall provide notice to the other party and to the JUA.
(2) If the JUA does not settle a dispute described in section (1) of this rule within 90 days of the notice, then either the pole owner or the pole occupant may request a hearing before the Commission and an order from the Commission to resolve the dispute:
(a) Upon receipt of a request, the Commission Staff shall, within 30 days, provide to the parties a recommended order for the Commission;
(b) Either party may, within 30 days of receipt of the recommended order, submit written comments to the Commission regarding the recommended order;
(c) Upon receipt of written comments, the Commission shall, within 30 days, issue an order.

Or. Admin. Code § 860-028-0220

PUC 15-2000, f. 8-23-00, cert. ef. 1-1-01; PUC 4-2001, f. & cert. ef. 1-24-01; PUC 23-2001, f. & cert. ef. 10-11-01, Renumbered from 860-022-0220 & 860-034-0920

Stat. Auth.: ORS 183, 756, 757 & 759

Stats. Implemented: ORS 756.040, 757.035, 757.270-290, 759.045 & 759.650-675