Or. Admin. Code § 812-002-0800

Current through Register Vol. 63, No. 12, December 1, 2024
Section 812-002-0800 - Work Period

"Work Period" as used in, OAR 812-003-0150, 812-004-0320, 812-004-0600, 812-004-1320 and 812-004-1600 means the time period from the date a contractor accepts a payment, offers a written proposal, enters into a contract or begins construction, whichever occurs first, until the date the contractual work is substantially completed by the contractor, or if not substantially completed, the date the work by the contractor ceased.

Or. Admin. Code § 812-002-0800

CCB 4-1998, f. & cert. ef. 4-30-98; CCB 8-1998, f. 10-29-98, cert. ef. 11-1-98; CCB 6-2000(Temp), f. 5-22-00, cert. ef. 5-22-00 thru 11-17-00; CCB 9-2000, f. & cert. ef. 8-24-00; CCB 9-2004, f. & cert. ef. 12-10-04; CCB 7-2005, f. 12-7-05, cert. ef. 1-1-06; CCB 6-2012, f. 4-25-12, cert. ef. 5-1-12

Stat. Auth.: ORS 670.310 & 701.235

Stats. Implemented: ORS 701.133, 701.139, 701.140, 701.145, & 701.146