Or. Admin. Code § 812-012-0170

Current through Register Vol. 63, No. 10, October 1, 2024
Section 812-012-0170 - Unpaid Court Judgments
(1) A contractor against whom a court enters a judgment or order awarding arbitration must report that judgment or order to the Construction Contractors Board, if:
(a) The judgment or order arises from:
(A) Breach of contract;
(B) Negligent work; or
(C) Improper work.
(b) The judgment or order relates to construction or proposed construction of a residential structure.
(2) The contractor will transmit a copy of the final judgment or order to the Construction Contractors Board within 45 days after the final judgment or order is recorded.
(3) The contractor will transmit the copy of the final judgment or order with a completed "Unpaid Court Judgment Filing" form described in OAR 812-001-0220.
(4) The contractor is not required to send the Board a copy of the judgment or order, if:
(a) The contractor paid the damages and other amounts payable under the judgment or order within 30 days from the date the judgment or order was recorded; or
(b) The contractor appealed the judgment or order and has filed an undertaking on appeal as required by ORS 19.300.

Or. Admin. Code § 812-012-0170

CCB 4-2009, f. 5-6-09, cert. ef. 6-1-09

Stat. Auth.: ORS 670.310 & 701.235

Stats. Implemented: ORS 701.109