Section 738-124-0050 - Department Review of COAR Applications
(1) The Department shall review applications for completeness and to confirm that Applicants and projects are eligible to receive funds. As part of its review, the Department may ask an Applicant to supply missing information or to provide clarification about Applicant or project eligibility.
(2) If an Application is incomplete, or an Applicant or project is ineligible, the Department shall, within 15 business days of making such determination:
(a) Specify in writing or email to the Applicant the additional information the Applicant must provide to complete the application or establish eligibility; or
(b) Notify the Applicant in writing or email that the Applicant or Project is ineligible and briefly describe the basis for ineligibility.
(3) If the Applicant fails to provide requested information within 10 business days from the date of the Department's written or email communication made pursuant to subsection (2)(a) of this rule, the Department may consider the application ineligible and provide the notice described in subsection (2)(b) of this rule.
(4) Affected Applicants may submit written protests of ineligibility determinations to the Director. Protests must be submitted in writing to the Director within 5 business days of the date of notice of the Department's determination of incompleteness or ineligibility that is being protested.
(5) The Director shall prepare a written response to the protest no later than 45 business days after the date the protest is received. The Director's written decision is final.

Or. Admin. Code § 738-124-0050

AVIA 1-2020, adopt filed 02/13/2020, effective 2/13/2020; AVIA 4-2022, amend filed 08/29/2022, effective 8/29/2022; AVIA 2-2024, amend filed 06/25/2024, effective 7/1/2024

Statutory/Other Authority: ORS 835.035, ORS 835.040, ORS 835.112 & ORS 319.023

Statutes/Other Implemented: ORS 835.025, ORS 835.035 & ORS 319.023