Or. Admin. Code § 635-009-0240

Current through Register Vol. 63, No. 11, November 1, 2024
Section 635-009-0240 - Grant Agreement
(1) Project sponsors, other than the Department, shall enter into a Grant Agreement with the Department prior to undertaking the project. The project sponsor shall obtain all necessary water rights, access agreements, easements, use permits or any other permits needed to undertake the project. Copies shall be provided prior to commencing the project.
(2) No funds shall be disbursed under a Grant Agreement until the Department receives satisfactory evidence that necessary permits and licenses have been granted and required documents submitted.
(3) Advance funds may be released upon presentation of a detailed estimate of expenses for a time period specified in the Grant Agreement. No additional funds will be released until all receipts for expenditures of a previous fund release are submitted.
(4) The project sponsor shall account for funds distributed by the Department, using project expense forms provided by the Department. Funds may be released upon presentation of a completed Fund Release Request Form accompanied by proof of completion of specific work elements of the project as identified in the Grant Agreement. Proof of completion may be made through presentation of paid receipts of invoices for materials of contracted labor, or inspection reports.
(5) The project sponsor shall agree to complete the project as approved by the Commission and within the time frame specified on the Grant Agreement.
(6) The project sponsor shall file a written request for permission to amend or expand the project or the time schedule including the rationale for the requested change. Proposed modifications shall be submitted and approved prior to the beginning of any work proposed in the modification.
(7) The project sponsor shall submit a project report at the completion of the project describing the work done.
(8) The project sponsor shall allow Commission, Board members, or Department staff, access to the project to monitor and evaluate the project.
(9) The project sponsor shall maintain the project for a period of time as deemed appropriate by the Commission.

Or. Admin. Code § 635-009-0240

FWC 86-1989, f. 8-31-89, cert. ef. 9-1-89; DFW 170-2019, amend filed 12/09/2019, effective 1/1/2020

Statutory/Other Authority: ORS 512

Statutes/Other Implemented: ORS 512