Or. Admin. R. 345-015-0380

Current through Register Vol. 63, No. 6, June 1, 2024
Section 345-015-0380 - Loss of Exemption
(1) In accordance with ORS 469.320(6), any person operating a facility for which the Council previously granted an exemption under ORS 469.320(2)(c) and that has experienced a substantial loss of steam host resulting in a substantial loss in fuel use efficiency must submit an application for a site certificate within 12 months of the loss.
(2) Any person proposing to enlarge the site of a facility previously determined to be exempt under 469.320(2)(a) must submit an application for a site certificate.
(3) Any person submitting an application for a site certificate under section (1) or (2) may request expedited review as described in OAR 345-015-0300 or 345-015-0310 if the average electric generating capacity of the energy facility is less than 100 megawatts.
(4) Any person operating a plant that the Council has determined exempt under OAR 345-015-0350(5) must apply for a site certificate before making any change in the operation of the plant such that the plant would no longer meet the requirements of ORS 469.320(2)(f).

Or. Admin. R. 345-015-0380

EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 4-1999(Temp), f. & cert. ef. 10-15-99 thru 4-11-00; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07

Stat. Auth.: ORS 469.373 & 469.470

Stats. Implemented: ORS 469.320