Or. Admin. R. 340-212-0230

Current through Register Vol. 63, No. 6, June 1, 2024
Section 340-212-0230 - Deadlines for Submittals
(1) Large regulated pollutant-specific emissions units. For all regulated pollutant-specific emissions units with the potential to emit the applicable regulated pollutant in an amount equal to or greater than 100 percent of the amount, in tons per year, required for a source to be classified as a major source, the owner or operator must submit the information required under OAR 340-212-0220 at the following times:
(a) The owner or operator must submit information as part of an application for an initial Oregon Title V Operating Permit if, by that date, the application either:
(A) Has not been filed; or
(B) Has not yet been determined to be complete by DEQ.
(b) The owner or operator must submit information as part of an application for a significant permit revision under OAR 340-218-0080, but only with respect to those regulated pollutant-specific emissions units for which the proposed permit revision applies;
(c) The owner or operator must submit any information not submitted under the deadlines set forth in subsections (1)(a) and (b) as part of the application for the renewal of an Oregon Title V Operating Permit.
(2) Other regulated pollutant-specific emissions units. For all other regulated pollutant-specific emissions units subject to OAR 340-212-0220 through 340-212-0280 and not subject to section (1), the owner or operator must submit the information required under 340-212-0220 as part of an application for a renewal of an Oregon Title V Operating Permit.
(3) A permit reopening to require the submittal of information under this rule is not required by OAR 340-218-0200(1)(a)(A). If, however, an Oregon Title V Operating Permit is reopened for cause by EPA or DEQ pursuant to OAR 340-218-0200(1)(a)(C), (D), or (E), the applicable agency may require the submittal of information under this rule for those regulated pollutant-specific emissions units that are subject to OAR 340-212-0200 through 340-212-0280 and that are affected by the permit reopening.
(4) Until DEQ approves monitoring plans that satisfy the requirements of OAR 340-212-0200 through 340-212-0280, the owner or operator is subject to the requirements of OAR 340-218-0050(3)(a)(C).

Or. Admin. R. 340-212-0230

DEQ 21-1998, f. & cert. ef. 10-14-98; DEQ 14-1999, f. & cert. ef. 10-14-99, Renumbered from 340-028-1230; DEQ 6-2001, f. 6-18-01, cert. ef. 7-1-01; DEQ 7-2015, f. & cert. ef. 4/16/2015

Stat. Auth.: ORS 468.020 & 468A.310

Stats. Implemented: ORS 468A.310