Current through Register Vol. 64, No. 1, January 1, 2025
Section 330-020-0050 - Extension of Submission Deadline(1) Any energy supplier that finds it cannot meet the deadline set forth in OAR 330-020-0045 may apply to the Director for an extension of time. The application shall be by petition setting forth: (a) The reasons why it cannot meet the deadline;(b) The measures it is taking to comply with the deadline; and(c) The date on which it expects to be able to supply the information.(2) The Director may grant an extension of not more than thirty days if it appears to him: (a) That the energy supplier is making a good faith effort to provide the information required in a timely manner; and(b) That it is likely that the energy supplier will be able to comply within the period of the extension.Or. Admin. Code § 330-020-0050
DOE 3, f. & ef. 11-20-75; DOE 7, f. & ef. 1-11-77; DOE 2-1978, f. & ef. 3-3-78; DOE 1-1979, f. & ef. 3-20-79; DOE 1-1984, f. 1-16-84, ef. 2-1-84Stat. Auth.: ORS 469
Stats. Implemented: ORS 469.080