Or. Admin. Code § 141-093-0145

Current through Register Vol. 63, No. 11, November 1, 2024
Section 141-093-0145 - Transportation-Related Structures - GP-Specific Application Requirements for Authorizing Projects
(1) Compensatory Mitigation. Unless otherwise approved by the Department, compensatory mitigation options are:
(a) Mitigation bank credit purchase from a Department-approved mitigation bank with a service area that includes the proposed removal-fill site and that meets the eligibility requirements for CM outlined in ORS 141-085-0690;
(b) In-lieu fee credit purchase that meets the eligibility requirements for CM outlined in ORS 141-085-0690; and
(c) Cash payment to the Department's payment in-lieu program.

Or. Admin. Code § 141-093-0145

DSL 3-2011, f. & cert. ef. 3-1-11; DSL 39-2018, minor correction filed 01/05/2018, effective 01/05/2018; DSL 43-2018, minor correction filed 01/05/2018, effective 1/5/2018; DSL 2-2019, amend filed 03/28/2019, effective 4/1/2019

Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990

Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990